
01 Assess
Asset retirement obligations and cost estimating
Independent engineering estimates of what it will cost to decommission, clear and restore an industrial asset, for the provision on the balance sheet and for the budget on the project. Built on real scopes, real hazards and real demolition prices.
01
Assess
02
Decommission
03
Demolish
04
Recover
05
Remediate


SAFETY AND COMPLIANCE
Safety first.
On every site, in every plan.
Assurance is designed into every stage, protecting people, programme and reputation from day one.
ISO
45001
Occupational health & safety
ISO
14001
Environmental management
ISO
9001
Quality management
ISO
SSIP
Cyber Essentials +
UK
TWF Member
Principal Designer capability
ISO
IDE
Subject Matter Experts
ISO
APS
APS Principal Designers
ISO
GLOBAL
Subject Matter Experts
OVERVIEW
The obligation is legal.
The number should be engineering.
Every industrial asset carries an obligation to be taken out of service, dismantled and the land put back to an agreed condition. It comes from permits, licences, leases, concession agreements and regulation, and accounting standards require it to be measured while the asset is still operating, as a decommissioning provision under IAS 37 and IFRIC 1, an asset retirement obligation under ASC 410-20, or a provision under FRS 102. Most provisions were set years ago as a percentage of capital cost and have been indexed since. Few were built from the asset as it stands.
We provide the engineering basis of the provision: the obligation mapped to its source, the end state defined, the asbestos and hazardous materials liability quantified, and a bottom-up estimate with programme, risk allowance and a register of every assumption, stated in today’s money so finance can apply inflation and discounting under the standard that applies. We also provide cost estimating, budgeting and cost control through the project itself, so the number that went into the accounts is the number the project is run to.
AT A GLANCE
STAGE
01 Assess
SITE TYPES
Refineries, terminals, power stations, chemical and pharmaceutical plants, nuclear licensed sites, manufacturing
REGIONS
Worldwide, from hubs in the United Kingdom and the UAE
STANDARDS
Estimates prepared to support IAS 37, IFRIC 1, ASC 410-20 and FRS 102 · ISO 9001 · 14001 · 45001
Scope
What's included
Everything finance, auditors and the project need from the engineering side of a decommissioning provision, and the cost control to deliver against it.
Obligation mapping
Isolation philosophy, sequence and verification agreed with the operator.
Review of existing provisions
Isolation philosophy, sequence and verification agreed with the operator.
End state and scope definition
Isolation philosophy, sequence and verification agreed with the operator.
Hazardous materials liability
Isolation philosophy, sequence and verification agreed with the operator.
Cost control through delivery
Isolation philosophy, sequence and verification agreed with the operator.
Engineering cost estimate
Isolation philosophy, sequence and verification agreed with the operator.

How we work
Four steps to a safe, prepared site
01
Map the obligation
Permits, licences, leases and regulation reviewed for what each requires at end of life.
02
Define and survey
End state and scope defined; asbestos and hazardous materials surveys scoped and managed.
03
Estimate and document
Quantities, methods, rates, programme, risk allowance and assumptions built up and recorded.
04
Support and update
Auditors’ questions answered; the estimate re-measured when the closure date, end state, surveys or market change.



