In brief
Circulis Group (formerly JAMES Ltd) led decommissioning and demolition management for mercury assets within a high-risk UK chemical complex undergoing phased closure. Because contamination varied, materials needed extensive sampling and analysis before they could be sentenced, and the client retained waste disposal costs with worst-case budgets in place. Discrete areas were let in stages through an alliance framework, using NEC4 Option A prices developed on an open-book basis.
Project at a glance
SECTOR
Chemical manufacturing
LOCATION
United Kingdom
PROJECT TYPE
Decommissioning and demolition of mercury assets within a chemical complex undergoing phased closure
OUR ROLE
Led decommissioning and demolition management for the client
COMMERCIAL MODEL
Alliance framework, with NEC4 Option A and an open-book approach
WASTE STRATEGY
Sampling and analysis to confirm recycling, reuse, off-site disposal or specialist landfill
KEY OUTCOME
Staged funding supported by reviewed proposals, with variations limited to additional work outside the scope

Home / Case Studies / Mercury decommissioning
UK
Decommissioning project management
Scrap, asset recovery and waste strategy
Chemical manufacturing
Mercury decommissioning and demolition case study:
Managing contaminated assets under an alliance framework
How waste characterisation, staged funding and an open-book NEC4 alliance supported the demolition of mercury-contaminated chemical assets in the UK.
4 min read
United Kingdom
Circulis Group (formerly JAMES Ltd)

On this page
01 Why are mercury assets harder to decommission?
Contamination within the process systems was variable, which meant a material’s disposal route could not be assumed. Extensive sampling and analysis were needed to confirm whether it could be recycled, reused or disposed of off site, or had to be sentenced to specialist landfill.
Some products that had to remain in place were also outside a typical demolition contractor’s skill set. Those two issues shaped how the project was funded, procured and delivered.
02 Who should carry waste cost risk on a contaminated demolition project?
Here, the client kept waste disposal costs. With contamination this variable, a contractor could only have priced that risk by making assumptions. Worst-case scenarios were budgeted so that the right provisions were in place from the start.
This does mean the client holds the exposure, so it relies on sound characterisation and realistic provisions.
03 Why were the works let in stages?
The scale of the project meant discrete areas were let in stages according to an initial strategy, with provisions applied for at each stage. Proposals were reviewed jointly by the demolition contractor and Circulis, which gave the cost certainty needed to support each funding application.
04 How did the alliance framework work?
The PCI and scope of works were issued under NEC4 Option A, and the client, Circulis and the demolition contractor worked together to consider and price the scope. The open-book approach gave full visibility and helped identify risks early.
The framework partnership also addressed the specialist capability issue. Working with a framework partner allowed the project team to develop the skills needed to handle the special products.
Regular consultation with the client’s procurement team made sure the NEC4 amendments suited demolition.
05 How were decommissioning end states and handover controlled?
Each process product had a risk-based decommissioning end point, developed in partnership with the client from its plant and product knowledge and Circulis procedures. The criteria considered what a demolition contractor could reasonably be expected to handle and identified where specialist capability would be needed.
Decommissioning activities were reviewed and audited against the system end states. Plant condition was recorded on system templates, and all handover documents were peer reviewed and signed off before feeding into the PCI and scope.
06 How were surveys and pre-construction information managed?
Circulis developed the scope for fixed-price hazardous insulating material (HIM) surveys. Survey reports were compiled to match the demolition areas and reviewed against HSG264, with quantities justified to avoid overstating or understating HIMs.
PCI and scope were developed through HAZDEM hazard reviews and signed off through committee review. Circulis also led regulator notifications and local authority engagement, and reflected local authority conditions in the scope.
07 How was the work controlled on site?
Safe systems of work followed a multi-stage gate process for development, issue and execution. Circulis cross-checked that relevant site information and hazards had been considered, supporting duty holders in meeting their own responsibilities, and assisted with site briefings, workforce communication and on-site execution reviews.
Valuations were reconciled with physical progress and benchmarked against milestones, while structured cost review boards examined forecasts and cost performance. The only variations to the demolition contract were additional works outside the scope.
08 How were programme and stakeholders managed?
A master programme linked the pre-demolition phases, decommissioning, contractor procurement, execution, remediation design and close-out, with the critical path managed throughout. The detailed decommissioning programme achieved its milestones on target and aligned with demolition contract award.
The demolition contractor’s programme was formally reviewed each fortnight, supported by daily and scheduled progress reviews. Circulis led consultation with stakeholders, including those involved in the demolition sequence.
OUTCOME
Results.What the client got.
4
Waste routes tested through sampling and analysis
3
Parties pricing each scope together on an open-book basis
NEC4 A
Every scope issued under Option A within the framework
On target
Detailed decommissioning programme milestones

Materials were characterised through sampling and analysis to establish their disposal route.

Provisions were in place for worst-case waste scenarios.

Staged funding applications were supported by reviewed proposals.

The only variations to the demolition contract were additional works outside the scope.

The detailed decommissioning programme was achieved on target.
For asset owners
Lessons for asset owners
01
Characterise before assuming a waste route
With variable contamination, sampling determines both disposal and budget.
02
Decide deliberately who holds waste risk
Keeping it can be more transparent than paying a contractor to price uncertainty, provided provisions are realistic.
03
Match the funding route to the delivery strategy
Staged lettings can work well where funding is also released in stages.
04
Check for skills gaps
Where products fall outside normal demolition capability, plan early how that capability will be developed or secured.