In brief

Circulis Group (formerly JAMES Ltd) led decommissioning and demolition management for mercury assets within a high-risk UK chemical complex undergoing phased closure. Because contamination varied, materials needed extensive sampling and analysis before they could be sentenced, and the client retained waste disposal costs with worst-case budgets in place. Discrete areas were let in stages through an alliance framework, using NEC4 Option A prices developed on an open-book basis.

Project at a glance
SECTOR

Chemical manufacturing

LOCATION

United Kingdom

PROJECT TYPE

Decommissioning and demolition of mercury assets within a chemical complex undergoing phased closure

OUR ROLE

Led decommissioning and demolition management for the client

COMMERCIAL MODEL

Alliance framework, with NEC4 Option A and an open-book approach

WASTE STRATEGY

Sampling and analysis to confirm recycling, reuse, off-site disposal or specialist landfill

KEY OUTCOME
Staged funding supported by reviewed proposals, with variations limited to additional work outside the scope
Dark Blue Technical Grid Background.png

Home / Case Studies / Mercury decommissioning

UK

Decommissioning project management

Scrap, asset recovery and waste strategy

Chemical manufacturing

Mercury decommissioning and demolition case study:

Managing contaminated assets under an alliance framework

How waste characterisation, staged funding and an open-book NEC4 alliance supported the demolition of mercury-contaminated chemical assets in the UK.

4 min read

United Kingdom

Circulis Group (formerly JAMES Ltd)

Programme.png

01  Why are mercury assets harder to decommission?

Contamination within the process systems was variable, which meant a material’s disposal route could not be assumed. Extensive sampling and analysis were needed to confirm whether it could be recycled, reused or disposed of off site, or had to be sentenced to specialist landfill.
 

Some products that had to remain in place were also outside a typical demolition contractor’s skill set. Those two issues shaped how the project was funded, procured and delivered.

02  Who should carry waste cost risk on a contaminated demolition project?

Here, the client kept waste disposal costs. With contamination this variable, a contractor could only have priced that risk by making assumptions. Worst-case scenarios were budgeted so that the right provisions were in place from the start.

​

This does mean the client holds the exposure, so it relies on sound characterisation and realistic provisions.

03  Why were the works let in stages?

The scale of the project meant discrete areas were let in stages according to an initial strategy, with provisions applied for at each stage. Proposals were reviewed jointly by the demolition contractor and Circulis, which gave the cost certainty needed to support each funding application.

04  How did the alliance framework work?

The PCI and scope of works were issued under NEC4 Option A, and the client, Circulis and the demolition contractor worked together to consider and price the scope. The open-book approach gave full visibility and helped identify risks early.
 

The framework partnership also addressed the specialist capability issue. Working with a framework partner allowed the project team to develop the skills needed to handle the special products.
 

Regular consultation with the client’s procurement team made sure the NEC4 amendments suited demolition.

05  How were decommissioning end states and handover controlled?

Each process product had a risk-based decommissioning end point, developed in partnership with the client from its plant and product knowledge and Circulis procedures. The criteria considered what a demolition contractor could reasonably be expected to handle and identified where specialist capability would be needed.
 

Decommissioning activities were reviewed and audited against the system end states. Plant condition was recorded on system templates, and all handover documents were peer reviewed and signed off before feeding into the PCI and scope.

06  How were surveys and pre-construction information managed?

Circulis developed the scope for fixed-price hazardous insulating material (HIM) surveys. Survey reports were compiled to match the demolition areas and reviewed against HSG264, with quantities justified to avoid overstating or understating HIMs.
 

PCI and scope were developed through HAZDEM hazard reviews and signed off through committee review. Circulis also led regulator notifications and local authority engagement, and reflected local authority conditions in the scope.

07  How was the work controlled on site?

Safe systems of work followed a multi-stage gate process for development, issue and execution. Circulis cross-checked that relevant site information and hazards had been considered, supporting duty holders in meeting their own responsibilities, and assisted with site briefings, workforce communication and on-site execution reviews.
 

Valuations were reconciled with physical progress and benchmarked against milestones, while structured cost review boards examined forecasts and cost performance. The only variations to the demolition contract were additional works outside the scope.

08  How were programme and stakeholders managed?

A master programme linked the pre-demolition phases, decommissioning, contractor procurement, execution, remediation design and close-out, with the critical path managed throughout. The detailed decommissioning programme achieved its milestones on target and aligned with demolition contract award.
 

The demolition contractor’s programme was formally reviewed each fortnight, supported by daily and scheduled progress reviews. Circulis led consultation with stakeholders, including those involved in the demolition sequence.

OUTCOME

Results.What the client got.

4

Waste routes tested through sampling and analysis​

3

Parties pricing each scope together on an open-book basis

NEC4 A

Every scope issued under Option A within the framework

On target

Detailed decommissioning programme milestones
check.png

Materials were characterised through sampling and analysis to establish their disposal route.

check.png

Provisions were in place for worst-case waste scenarios.

check.png

Staged funding applications were supported by reviewed proposals.

check.png

The only variations to the demolition contract were additional works outside the scope.

check.png

The detailed decommissioning programme was achieved on target.

For asset owners

Lessons for asset owners

01

Characterise before assuming a waste route

With variable contamination, sampling determines both disposal and budget.​

02

Decide deliberately who holds waste risk

Keeping it can be more transparent than paying a contractor to price uncertainty, provided provisions are realistic.

03

Match the funding route to the delivery strategy

Staged lettings can work well where funding is also released in stages.

04

Check for skills gaps

Where products fall outside normal demolition capability, plan early how that capability will be developed or secured.

Client-Side Support Banner.png
group
Client-side support

Where independent client-side support helps

On contaminated assets, a client-side engineer can help owners test waste assumptions, review contractor proposals on an open-book basis and keep funding applications tied to credible scope.

Owner’s Engineer and technical assurance Discuss your project